Project Vita, Coventry
Project Overview
· Client: SES Engineering Services
· Location: Coventry
· Duration: 12 months
D & T Mechanical was contracted to supply and install piped services for two new-build student accommodation towers (13 and 11 storeys), serving nearly 500 apartments in the city centre.
Key works included:
· New plantroom installation: boilers, pumps, CHP, buffer vessels, hot water heaters, water storage tanks and booster sets.
· Domestic services: full press-fit installation serving kitchens and podded bathrooms.
· Drainage systems: cast iron and solvent weld above-ground drainage and rainwater pipework.
The Challenge
This was a fast-moving build with a programme that constantly shifted to meet deadlines. The pace demanded a responsive mechanical partner able to flex resource and support early delivery targets.
D & T Mechanical's Role
SES brought D & T Mechanical on board after a trusted supplier recommendation, and because of their reputation for reliability and delivery.
What made D & T stand out:
· Collaborative mindset: a “let’s get this done” attitude with a common-sense approach.
· Responsive resourcing: providing labour when and where it was needed.
The Results
D & T Mechanical integrated seamlessly with SES’s project team, helping maintain programme pace and achieving high-quality delivery. Their proactive approach not only met the immediate project needs but also secured future contracts with SES.
Client Feedback
“With D & T, you don’t feel like you’re employing a business, you’re bringing an extension to your project team. They’re collaborative, reliable and invested in the success of the job. I’ve recommended them many times and will continue to do so.” Steve Spooner, Project Manager, SES Engineering Services