Project Vita, Coventry

Duration: Ongoing

Supply and install piped services to a 13-storey and 11-storey new build tower blocks for student accommodation in the centre of Coventry.

New plantroom consisting of boilers, pumps, CHP, buffer vessels, hot water heaters, water storage tank and booster set.

Press fit installation of the domestic services serving 280+ apartments complete with kitchen sink and podded bathrooms.

Cast iron and solvent weld above-ground drainage and rainwater pipework serving the building.